Administrative Manual - Nov 2026

Part 2. Application Review Procedures 2.3 Common Application Procedures

Things to Know  Where a Site Plan Approval application is submitted concurrently with a Construction Plan Approval application, the applicant benefits from a more streamlined review, but incurs greater up- front costs in preparing detailed plans and the risk of greater costs that might be involved if such plans have to be substantially revised multiple times. A Transportation Impact Analysis is required for site plans.  Combined Site Plan and Construction Plan applications will pay both fees, outlined in the fee schedule, for each application but will receive an additional review included in the fees.  Any changes to a site plan after it is accepted for review will likely cost the applicant additional time and fees.  Site Plan Approval expires if no significant work is done pursuant to the approval within two years after the date of approval.  Staff decisions on a Site Plan Approval application may be appealed to the Planning and Zoning Board through the Administrative Appeal procedure.

Site Plan Approval

• Site Plan Approval by the Planning Director is required for any of the following developments, unless specifically exempted in the UDO:  Development in accordance with a valid Planned Development (PD) Plan/Agreement;  Development in accordance with a valid Conceptual Master Plan Approval;  Development in accordance with a valid Special Use Permit approval; 

Development of any principal use designated in UDO Table 4.2.4, Principal Use Table, as permitted with Site Plan Approval by Town staff;  Accessory uses and structures; and  Temporary uses and structures. • See Section 2.5.7 in the UDO for specific application procedures. Subdivision Approval Preliminary Plat Approval • There are two types of preliminary plat subdivision approvals: Type 1 and Type 2. The following summarizes these two types of subdivisions:  A Type 2 Subdivision is any preliminary plat proposing single-family detached, attached, or duplex dwellings voluntarily complying with Section 5.9.7 of the Unified Development Ordinance. • See Section 2.5.6 in the UDO for specific application procedures. Final Plat Approval • The final step in the Subdivision Approval process is the final plat recordation. • See Section 2.5.6 in the UDO for specific application procedures. Determination of Subdivision Exclusion • An application for a Determination of Subdivision Exclusion must meet one of the activities specifically Things to Know  A Type 1 or Type 2 Subdivision Preliminary Plat Approval expires if no significant work is done in two years.  If a development requires payment in lieu of providing required public recreation area, the payment is due to the Town before recording the approved Final Plat.  Final Plats expire if the applicant fails to record the plat within 30 days after the approval.  Recorded Final Plats do not expire. A Type 1 Subdivision is any preliminary plat proposing single-family detached, attached, or duplex dwellings not voluntarily complying with Section 5.9.7 of the Unified Development Ordinance. 

listed as excluded from the definition of “subdivision” in the UDO. • See Section 2.5.6 in the UDO for specific application procedures.

November 1, 2026 Page 2-4

Morrisville, NC Administrative Manual