Comprehensive Transportation Plan - March 2019
PROJECT SHEETS
NC 54 (Chapel Hill Road)
2010 – n/a Widening
Length 0.46 miles
Project Extents
From: Northern Town Limits near Shiloh Glenn Drive To: NC 540
Traffic Volume (vpd) Street Hierarchy 2010 – 21,956 2040 – 51,730 Major Thoroughfare Congestion (v/c ratio)
Planning Cost Estimate July 2017
2010 – 0.60 2040 – 0.68
$10,302,000 Crash Summary (June 2013 to May 2016) Total Crashes – 15 EPDO Score – 120.4
CROSS-SECTION
KEY STANDARD DIMENSIONS
NOTES:
11-ft inside lanes
12-ft dedicated bus lane
Town staff can consider alternative dimensions and alternative accommodations for bicycles and pedestrians. Bus lanes can be center-running or in the outside lanes as shown in the cross-section.
17.5-ft planted median
0-ft to 10-ft verge 10-ft sidepath east side of roadway 5-ft sidewalk