Part 4. Appendices 4.9 Review Schedules

4.9 REVIEW SCHEDULES Each of the review schedules represents average time within which a decision may be reached. Some development applications may require additional review time to resolve issues that may arise in the staff review and/or board review and decision process. The amount of time it takes an applicant to revise an application to correct deficiencies as well the overall quality of each submittal impacts the overall review time.

4.9.1

Planning and Zoning Board Quasi-Judicial Decision Review Schedule

Planning and Zoning Board Quasi-Judicial Decision Estimated Review Schedule

Planning and Zoning Board Meeting [4] 12/11/2025 01/08/2026 02/12/2026 03/12/2026 04/09/2026 05/14/2026 06/11/2026 07/09/2026 08/13/2026 09/10/2026 10/08/2026 11/12/2026 12/10/2026 01/14/2027 02/11/2027 03/11/2027 04/08/2027 05/13/2027

If Application Accepted for Review by Date Below

Initial Staff Review Due

Agenda Posted to the Web

08/01/2025 09/01/2025 10/01/2025 11/01/2025 12/01/2025 01/01/2026 02/01/2026 03/01/2026 04/01/2026 05/01/2026 06/01/2026 07/01/2026 09/01/2026 10/01/2026 11/01/2026 12/01/2026 01/01/2027

09/01/2025 10/01/2025 11/01/2025 12/01/2025 01/01/2026 02/01/2026 03/01/2026 04/01/2026 05/01/2026 06/01/2026 07/01/2026 08/01/2026 09/01/2026 10/01/2026 11/01/2026 12/01/2026 01/01/2027 02/01/2027

12/05/2025 01/02/2026 02/06/2026 03/06/2026 04/03/2026 05/08/2026 06/05/2026 07/03/2026 08/07/2026 09/04/2026 10/02/2026 11/06/2026 12/04/2026 01/08/2027 02/05/2027 03/05/2027 04/02/2027 05/07/2027

Submit Application [1]

Completeness Review [2] [3] 08/01/2026

Notes: [1] Applications can be submitted any time through the Town of Morrisville Customer Self Service Online Portal here. [2] The applicant will receive notice of submittal deficiencies or submittal acceptance through the online portal within 2 business days from the time of submission. Review of an application does not start until staff determines it to be complete, accepts the application for review, and enters an application into the monthly review cycle. [3] Time needed to correct application submittal deficiencies and resubmit a complete application is the responsibility of the applicant. If the applicant fails to resubmit a complete application within 30 days, the application is considered abandoned. [4] Board meetings begin at 6:30 p.m. in the Town Hall Council Chambers (100 Town Hall Drive, Morrisville, NC 27560).

Morrisville, NC Administrative Manual

August 7, 2023 Page 88