FY2020 Budget

CIP Project:

Crabtree Hatcher Creek Greenway Loop

Project Category:

Bicycle & Pedestrian

Site:

FromMorrisville Parkway to the end of Crabtree Crossing Parkway where Crabtree Hatcher Creek Greenway starts.

Improve greenway connectivity from the Crabtree Hatcher Creek Greenways by extending a multi-use path about 0.50 miles along Crabtree Crossing fromMorrisville Parkway to current greenway end, within existing ROW.

Description:

Picture/Map:

Serves the interest of mobility and connectivity. The upated CTP indicates the need for a sidewalk on both sides of road to be in compliance. A sidewalk segment exists currently on the southwest side of roadway. This project could also be considered a sidewalk gap projectrather than a greenway connection. This project will improve connectivity and promote non-vehicular transportation as an extension from the Crabtree Hatcher Creek Greenway. The recent needs assessment survey indicated the top two desired amenities were walking trails and linked greenways, and is included in the Parks & Greenways Master Plan. Project could possibly qualify for grant funding through CAMPO or other transportation related options.

Justification:

Other Considerations:

Preliminary Estimate

$

660,000

Includes: ROW, Design and Construction

All projects include in estimate a 25% contingency based on construction cost.

Strategic Goal:

Improved Transportation Mobility