4.9 REVIEW SCHEDULES Each of the review schedules represents average time within which a decision may be reached. Some development applications may require additional review time to resolve issues that may arise in the staff review and/or board review and decision process. The amount of time it takes an applicant to revise an application to correct deficiencies as well the overall quality of each submittal impacts the overall review time.

4.9.1

Planning and Zoning Board Quasi-Judicial Decision Review Schedule

Planning and Zoning Board Quasi-Judicial Decision Estimated Review Schedule

Deadline to Enter Monthly Review Cycle [3]

Planning and Zoning Board Meeting [4] 12/14/2023 01/11/2024 02/08/2024 03/14/2024 04/11/2024 05/09/2024 06/13/2024 07/11/2024 08/08/2024 09/12/2024 10/10/2024 11/14/2024 12/12/2024 01/09/2025 02/13/2025 03/13/2025 04/10/2025 05/08/2025

Initial Staff Review Due

Agenda Posted to the Web

08/01/2023 09/01/2023 10/01/2023 11/01/2023 12/01/2023 01/01/2024 02/01/2024 03/01/2024 04/01/2024 05/01/2024 06/01/2024 07/01/2024 09/01/2024 10/01/2024 11/01/2024 12/01/2024 01/02/2025

09/01/2023 10/01/2023 11/01/2023 12/01/2023 01/01/2024 02/01/2024 03/01/2024 04/01/2024 05/01/2024 06/01/2024 07/01/2024 08/01/2024 09/01/2024 10/01/2024 11/01/2024 12/01/2024 01/02/2025 02/01/2025

12/08/2023 01/05/2024 02/02/2024 03/08/2024 04/05/2024 05/03/2024 06/07/2024 07/05/2024 08/02/2024 09/06/2024 10/04/2024 11/08/2024 12/06/2024 01/03/2025 02/07/2025 03/08/2025 04/04/2025 05/02/2025

Submit Application [1]

Completeness Review [2] 08/01/2024

Notes: [1] Applications can be submitted any time through the Town of Morrisville Customer Self Service Online Portal here. [2] The applicant will receive notice of submittal deficiencies or submittal acceptance through the online portal within 2 business days from the time of submission. Review of an application does not start until staff determines it to be complete, accepts the application for review, and enters an application into the monthly review cycle. [3] Time needed to correct application submittal deficiencies and resubmit a complete application is the responsibility of the applicant. If the applicant fails to resubmit a complete application within 30 days, the application is considered abandoned. [4] Board meetings begin at 6:30 p.m. in the Town Hall Council Chambers (100 Town Hall Drive, Morrisville, NC 27560).

Morrisville, NC