Morrisville UDO Administrative Manual - February 2020

Part 4 Appendices Checklists

4.5.30

Telecommunications Facility Collocation/Modification

Telecommunications Facility Collocation/Modification Submittal Checklist For each listed item, check (√) if provided, write “n/a” if the feature does not exist or is not proposed, and write “w” if a waiver from the requirement is justified because it is unnecessary in the particular case to determine compliance with applicable regulations. Staff Use Only √, n/a, or w Application Submittal Requirement √, n/a, or w A Documents to be Submitted

1

Fee payment

2 A detailed written explanation (submitted electronically) of the circumstances necessitating the change 3 11"x 17" prepared and sealed by a qualified design professional

B

Complete Site Plans of the proposed changes

1 Existing conditions displayed in the background of the site plan in grayscale

2 Proposed changes must be shown in bold and all corresponding elements must be labeled

3

Strike-through items being removed or changed

4 If needed, the site plan must include a reference to relevant construction detail(s)

5 Additional construction detail(s) must be provided on the site plan or a separate sheet

6

Title block

• Site plan name and submittal date

• Tower number and address

• Town project and file numbers

7

North arrow

8

Graphic and numeric scale

C

Other

1 A statement on letterhead from a qualified individual that the applicant will comply with all FCC rules regarding human exposure to radio frequency (RF) energy, along with the individual’s qualifications 2 A statement on letterhead from a qualified individual that the applicant will comply with all FCC rules regarding RF interference 3 A structural certification by a Registered Professional Engineer that the facility complies and will continue to comply with EIA/TIA-222-G (as amended) for Wake County, NC 4 Supplemental information may be requested for purposes of clarify or confirmation

4.5.31

Telecommunications Facility New Tower

New Telecommunication Facility Construction Plan Approval for a Site Plan (Major or Minor) Submittal Checklist For each listed item, check (√) if provided, write “n/a” if the feature does not exist or is not proposed, and write “w” if a waiver from the requirement is justified because it is unnecessary in the particular case to determine compliance with applicable regulations. Staff Use Only √, n/a, or w Application Submittal Requirement √, n/a, or w A Documents to be Submitted 1 Sets of plans – 24"x36"

2 Elevation and bench-marks referenced to National Geodetic Vertical Datum (NGVD) 3 Compact disc of plans with a PDF of each submitted plan sheet and all reports/documents 4 Request for No Practical Alternatives Determination / Request for Buffer Authorization (for any proposed impacts to riparian buffers)

September 13, 2019

Morrisville, NC

Page 4-64

Administrative Manual

Made with FlippingBook flipbook maker