Morrisville UDO Administrative Manual - May 2020
Part 4. Appendices 4.9 Review Schedules
4.9 REVIEW SCHEDULES Each of the review schedules represents average time within which a decision may be reached. Some development applications may require additional review time to resolve issues that may arise in the staff review and/or board review and decision process. The amount of time it takes an applicant to revise an application to correct deficiencies as well the overall quality of each submittal impacts the overall review time.
4.9.1
Board of Adjustment Decision Review Schedule
Board of Adjustment Decision Estimated Review Schedule
Deadline to Enter Monthly Review Cycle [3]
Initial Staff Review Due
Staff Report Posted to the Web
Board of Adjustment Meeting [4]
01/02/2020 02/03/2020 03/02/2020 04/01/2020 05/01/2020 06/01/2020 07/01/2020 08/03/2020 09/01/2020 10/01/2020 11/02/2020 12/01/2020 02/01/2021 03/01/2021 04/01/2021 05/03/2021 06/01/2021
02/03/2020 03/02/2020 04/01/2020 05/01/2020 06/01/2020 07/01/2020 08/03/2020 09/01/2020 10/01/2020 11/02/2020 12/01/2020 01/04/2021 02/01/2021 03/01/2021 04/01/2021 05/03/2021 06/01/2021 07/01/2021
07/07/2018 08/03/2018 09/04/2018 10/05/2018 11/02/2018 12/07/2018 01/04/2019 02/01/2019 03/01/2019 04/05/2019 05/03/2019 06/07/2019 07/05/2019 08/02/2019 09/06/2019 10/04/2019 11/01/2019 12/06/2019
07/11/2018 08/08/2018 09/12/2018 10/10/2018 11/14/2018 12/12/2018 01/09/2019 02/13/2019 03/13/2019 04/10/2019 05/08/2019 06/12/2019 07/10/2019 08/14/2019 09/11/2019 10/09/2019 11/13/2019 12/11/2019
Submit Application [1]
Completeness Review [2] 01/04/2021
Notes: [1] Applications can be submitted any time through the Town of Morrisville Customer Self Service Online Portal by visiting www.TownofMorrisville.org. [2] The applicant will receive notice of submittal deficiencies or submittal acceptance through the online portal within 2 business days from the time of submission. Review of an application does not start until staff determines it to be complete, accepts the application for review, and enters an application into the monthly review cycle. [3] Time needed to correct application submittal deficiencies and resubmit a complete application is the responsibility of the applicant. If the applicant fails to resubmit a complete application within 30 days, the application is considered abandoned. [4] Board meetings begin at 6:30 p.m. in the Town Hall Council Chambers (100 Town Hall Drive, Morrisville, NC 27560).
Morrisville, NC
May 29, 2020
Administrative Manual
Page 4-82
Made with FlippingBook HTML5