Morrisville UDO Administrative Manual, version August 1, 2018
Part 4 Appendices 4.9 Review Schedules
B. Legislative Review Schedules
1. Comprehensive Plan Amendment and General Rezoning
Comprehensive Plan Amendment and General Rezoning Review Schedule
Town Council Decision Meeting [8][9]
Planning & Zoning Board Meeting [8]
Town Council Public Hearing [8]
Deadline to Enter Monthly Review Cycle
Staff Report Posted to the Web
Town Council Meeting [8]
Initial Staff Review
07/02/2018
08/01/2018
09/07/2018 09/13/2018 10/09/2018 10/23/2018 11/13/2018
10/01/2018
10/31/2018
12/07/2018 12/13/2018 01/08/2019 01/22/2019 02/12/2019
02/01/2019
01/02/2019
03/01/2019 03/14/2019 04/09/2019 04/23/2019 05/14/2019
05/01/2019
04/01/2019
06/07/2019 06/13/2019 07/09/2019 07/23/2019 08/13/2019
07/31/2019
07/01/2019
09/06/2019 09/12/2019 10/08/2019 10/22/2019 11/12/2019
10/01/2019
10/31/2019
12/06/2019 12/12/2019 01/14/2020 01/28/2020 02/11/2020
Pre-Application Conference [2] Submit Application [3][4] 01/02/2020 04/01/2020
02/03/2020
03/06/2020 03/12/2020 04/14/2020 04/28/2020 05/12/2020
Revisions to Application [7]
Completeness Review [5][6]
05/01/2020
06/05/2020 06/11/2020 07/14/2020 07/28/2020 08/11/2020
Pre-Application Materials Deadline [1] 07/01/2020
07/31/2020
09/04/2020 09/10/2020 10/13/2020 10/27/2020 11/10/2020
12/01/2020
01/07/2021
02/05/2021 02/11/2021 03/09/2021 03/23/2021 04/13/2021
Notes: [1] At least two business days before a scheduled pre-application conference, the applicant shall submit a conceptual plan or drawings showing the location, general layout, and main elements of the proposed development application. [2] A pre-application conference with staff is required or strongly encouraged for all applications (see UDO for specific application requirements). It is recommended to have a pre-application conference at least six weeks prior to application submittal. [3] Complete applications can only be dropped off at the Planning Department (260 Town Hall Drive, Suite B, Morrisville, NC 27560) on Wednesdays between 8 am and noon. See checklist and Section 2.4.3, Application Submittal, Acceptance, Revisions, and Withdrawal, of the UDO for specific requirements. [4] The Town recommends dropping off a complete application 2-3 weeks prior to date listed in the Deadline to Enter Monthly Review Cycle. Dropping off an application prior to the deadline date does not guarantee an application will enter that review cycle. [5] Staff provides the applicant written notice of submittal deficiencies or submittal acceptance by Friday (2 days). Review of an application does not start until staff determines it to be complete, accepts the application for review, and enters an application into the monthly review cycle. [6] Time needed to correct application submittal deficiencies and resubmit a complete application is the responsibility of the applicant. If the applicant fails to resubmit a complete application within 30 days, the application is considered abandoned. [7] This step typically occurs 1-2 times. Time needed to review revised applications varies with the extent of staff comments and responding revisions. If the applicant fails to submit a revised application within 15 days of receiving staff comments, the review time will most likely take longer than this published timeline. If the applicant fails to submit a revised application within 60 days (or staff-granted extension), the application is considered withdrawn. [8] Meetings are at 6:30 p.m. in the Town Hall Council Chambers (100 Town Hall Drive, Morrisville, NC 27560). [9] Staff provides applicant written notice of Town Council’s decision to approve the application, approve it with condition, or deny the application. The overall timeline is impacted by the complexity of the process and actions taken by the boards such as tabling an item or cancelling a meeting.
Morrisville, NC
August 1, 2018
Administrative Manual
Page 4-101
Made with FlippingBook Online newsletter