Morrisville Unified Development Ordinance - June 2017
Article 2: Administration Section 2.5. Application-Specific Review Procedures 2.5.25. Wireless Telecommunication Facilities
(i)
Continue to comply with this Ordinance;
Wireless Telecommunication Facilities Requiring a Major Site Plan
(ii) Are necessary to comply with conditions of approval; (iii) Comply with the policies set forth in the Town of Morrisville Wireless Telecommunication Facilities Master Plan; or (iv) Are consistent with the Special Use Permit approval or any Town Council approval on which the Special Use Permit approval was based. Consistency means the changes would not significantly alter the developmentās general function, form, intensity, character, demand on public facilities, impact on adjacent properties, or other characteristic from that indicated by the Special Use Permit approval or any prior Town Council approval on which it was based. In any case, the following change from the Special Use Permit for Wireless Telecommunication Facilities approval on which it was based shall constitute a major change requiring amendment of the Special Use Permit in accordance with Section 2.4.8.D Modification or Amendment of Approval:
Step is Applicable
Step is Not Applicable
Pre-Application Conference
Application Submittal and Acceptance
Staff Review and Recommendation with DRC review
(B)
Scheduling and Notice of Meetings
Planning and Zoning Board Review and Recommendation
(i)
A change in a condition of approval.
(ii) A change in the height of the facility.
(iii) A change in the size of the compound area.
Town Council Review and Decision
(C)
Before determining whether a change is a minor change or a major change, the Planning Director shall review the record of the proceedings on the Special Use Permit application and consider whether any proposed modification would require evidentiary support in addition to that on which approval of the Special Use Permit application was based.
Figure 2.5.25.C.2
Major Site Plan Figure 2.5.25.C.2 and the following subsections identify those steps in the standard review procedure (see Section 2.4) applicable to the review of Wireless Telecommunication Facilities application requiring a Major Site Plan and note any specific variations of, or additions to, those review steps.
a. Pre-Application Conference
The applicant shall hold a pre-application conference with Town staff in accordance with Section 2.4.2.
b. Application Submittal and Acceptance
The application shall be submitted and accepted, and may be withdrawn, in accordance with Section 2.4.3.
June 23, 2017
Morrisville, NC
Page 2-78
Unified Development Ordinance
Made with FlippingBook - professional solution for displaying marketing and sales documents online