Morrisville Unified Development Ordinance - October 2021
Article 2: Administration Section 2.5. Application-Specific Review Procedures 2.5.25. Wireless Telecommunication Facilities
function, form, intensity, character, demand on public facilities, impact on adjacent properties, or other characteristic from that indicated by the Special Use Permit approval or any prior Town Council approval on which it was based. In any case, the following change from the Special Use Permit for Wireless Telecommunication Facilities approval on which it was based shall constitute a major change requiring amendment of the Special Use Permit in accordance with Section 2.4.8.D Modification or Amendment of Approval:
Wireless Telecommunication Facilities Requiring a Site Plan
Pre-Application Conference
b.
Application Submittal and Acceptance
(i)
A change in a condition of approval.
Staff Review and Planning Director Decision with DRC review
(ii) A change in the height of the facility.
(iii) A change in the size of the compound area.
c. Before determining whether a change is a minor change or a major change, the Planning Director shall review the record of the proceedings on the Special Use Permit application and consider whether any proposed modification would require evidentiary support in addition to that on which approval of the Special Use Permit application was based. Site Plan The following subsections identify those steps in the standard review procedure (see Section 2.4) applicable to the to the review of Wireless Telecommunication Facilities application requiring a Site Plan, or additions to, those review steps.
2.
a. Pre-Application Conference
The applicant shall hold a pre-application conference with Town staff in accordance with Section 2.4.2.
b. Application Submittal and Acceptance
The application shall be submitted and accepted, and may be withdrawn, in accordance with Section 2.4.3. Staff Review and Decision The Planning Director shall review the application, allow revisions of the application, and decide the application in accordance with Section 2.4.4 and Section 2.5.7. The decision shall be one of the following:
c.
(1) Approve the application as submitted;
(2) Approve the application subject to conditions; or
(3) Deny the application.
d. Post-Decision Actions
The post-decision actions and limitations in Section 2.4.8 shall apply to the application except as follows:
(1) Effect of Approval
Site Plan Approval for Wireless Telecommunication Facilities allows the approval of any concurrently-reviewed applications for Construction Plan Approval, Floodplain Management Permit, Stormwater Management Permit, Administrative Adjustment, or
Morrisville, NC
October 1, 2021
Unified Development Ordinance
Page 2-74
Made with FlippingBook Online newsletter creator