Article 2: Administration Section 2.5. Application-Specific Review Procedures 2.5.25. Wireless Telecommunication Facilities
(B) In any case, the following changes from the Major Site Plan Approval for Wireless Telecommunication Facilities shall constitute a major change requiring amendment of the Major Site Plan Approval in accordance with Section 2.4.8.D Modification or Amendment of Approval:
(i) A change in a condition of approval. (ii) A change in the height of the facility. (iii) A change in the size of the compound area.
Minor Site Plan Figure 2.5.25.C.3 and the following subsections identify those steps in the standard review procedure (see Section 2.4) applicable to the to the review of Wireless Telecommunication Facilities application requiring a Minor Site Plan, or additions to, those review steps. a. Pre-Application Conference The applicant shall hold a pre-application conference with Town staff in accordance with Section 2.4.2. b. Application Submittal and Acceptance The application shall be submitted and accepted, and may be withdrawn, in accordance with Section 2.4.3. c. Staff Review and Decision The Planning Director shall review the application, allow revisions of the application, and decide the application in accordance with Section 2.4.4 and Section 2.5.7.D. The decision shall be one of the following: (1) Approve the application as submitted; (2) Approve the application subject to conditions; or (3) Deny the application. d. Post-Decision Actions The post-decision actions and limitations in Section 2.4.8 shall apply to the application except as follows: (1) Effect of Approval Minor Site Plan Approval for Wireless Telecommunication Facilities allows the approval of any concurrently-reviewed applications for Construction Plan Approval, Floodplain Management Permit, Stormwater Management Permit,
Wireless Telecommunication Facilities Requiring a Minor Site Plan
Step is Applicable
Step is Not Applicable
Pre-Application Conference
Application Submittal and Acceptance
Staff Review and Planning Director Decision with DRC review
Scheduling and Notice of Meetings
Planning and Zoning Board Review and Recommendation
Town Council Review and Decision
Figure 2.5.25.C.3
Administrative Adjustment, or Alternative Equivalent Compliance for the same development. It also authorizes submittal of any other development applications that may be required before construction or use of the development authorized by the Minor Site Plan Approval. (2) Expiration of Approval A Minor Site Plan Approval for Wireless Telecommunication Facilities shall expire if no significant work is done or development is made within two years after the date of Minor Site Plan Approval.