Updated Working DRAFT UDO_Adopted Version_July 2024
Article 2: Administration Section 2.5. Application-Specific Review Procedures 2.5.15. Certificate of Compliance/Occupancy
2.5.15. Certificate of Compliance/Occupancy
A. Certificates of Compliance/Occupancy are approved and issued by the Building Official in accordance with review procedures and standards in the State Building Code. A Certificate of Compliance/Occupancy is required before a structure being developed in accordance with a Building Permit may be occupied or used for its authorized purpose. It certifies that work on the structure is completed in compliance with the Building Code and the terms and conditions of a Building Permit, but also in compliance with all other applicable Town regulations, including those in this Ordinance. A Certificate of Compliance/Occupancy serves as a final check on a structure’s compliance with the requirements of this Ordinance. Approval and issuance of a Certificate of Compliance/Occupancy does not preclude any responsibilities to obtain licenses and other approvals. B. No Certificate of Compliance/Occupancy shall be issued for a structure except in accordance with all prior approvals. Issuance of a Certificate of Compliance/Occupancy does not preclude requirements for licenses and other approvals.
2.5.16. Interpretation
A. Purpose
The purpose of this section is to provide a uniform mechanism for rendering formal written interpretations of this Ordinance. B. Authority
Responsibility for making interpretations of provisions of this Ordinance is assigned as follows:
1. The Planning Director shall be responsible for all interpretations of the zoning and subdivision provisions in the text of this Ordinance, including, but not limited to, interpretations of compliance with a condition of approval, and interpretations of whether an unspecified use falls within a use classification, use category, or use type allowed in a zoning district. The Planning Director shall also be responsible for interpretations of the zoning district boundaries on the Official Zoning Map. 2. The Town Engineer shall be responsible for all interpretations of the riparian buffer, stormwater management, and engineering provisions in the text of this Ordinance. 3. The Building Official shall be responsible for all interpretations of Building Code provisions as they relate to this Ordinance including interpretations relating to issuance of a Certificate of Compliance/Occupancy. C. Interpretation Procedure The following subsections identify those steps in the standard review procedure (see Section 2.4) applicable to the review of an Interpretation application and note any specific variations of, or additions to, those review steps. Application Submittal and Acceptance The application shall be submitted and accepted, and may be withdrawn or revised, in accordance with Section 2.4.3, except that it may be initiated by the Town Council, the Planning and Zoning Board, any resident or landowner in the town, or any person having a contractual interest in land in the town. Staff Review and Decision The Planning Director shall review the application and render a decision in accordance with Section 2.4.4, except that the decision shall be in the form of a written interpretation and the Planning Director shall consult with the Town Attorney and affected Town officials before rendering the interpretation. 1. 2.
Morrisville, NC
July 1, 2024 Page 2-54
Unified Development Ordinance
Made with FlippingBook - Online Brochure Maker