Comprehensive Transportation Plan - March 2019

Davis Drive

2010 – n/a Widening

Length 3.88 miles

Project Extents

From: Development Drive To: Morrisville-Carpenter Road

Traffic Volume (vpd) Street Hierarchy 2010 – 31,500 2040 – 37,100 Major Thoroughfare Congestion (v/c ratio)

Planning Cost Estimate July 2017 $62,595,000 1 1 This cost is for the full 3.88 miles. Only 1.4 miles is within the Town’s jurisdiction, resulting in approximately $23 million. Crash Summary (June 2013 to May 2016) Total Crashes – 201 EPDO Score – 646.8

2010 – 0.66 2040 – 0.78

CROSS-SECTION

KEY STANDARD DIMENSIONS

NOTES:

11-ft inside lanes 12-ft dedicated bus lane

12-ft dedicated bus lanes

Town staff can consider alternative dimensions and alternative accommodations for bicycles and pedestrians. Bus lanes can be center-running or in the outside lanes as shown in the cross-section.

17.5-ft planted median

0-ft to 10-ft verge

10-ft sidepath

C-6 | PAGE

Made with FlippingBook - Online Brochure Maker