Morrisville Public Transportation Study
Service & Financial Plan
feasible, it is recommended Morrisville lease the vehicles to begin with to save initial cost and speed up implementation. Table 9 | Smart-Shuttle Vehicle Cost
Vehicle Procurement
Unit Cost
Number of Units
Total Cost
Buy
$150,000
3
$450,000
Lease
$172,000
3
$516,000
Nodes Nodes are designed to provide customers with a waiting area. To initially start the system, Morrisville can simply install a boarding sign near a wheelchair accessible sidewalk. However, to ensure the system is comfortable and inviting to customers, Morrisville should provide additional amenities at each node (see Table 10). Within Morrisville, there are two tiers of nodes identified, the standard and advanced node. Table 11 provides the total costs of the nodes based on the type of node and selected locations. Table 10 | Node Amenity Costs
Amenity
Node Type
Cost
Boarding sign with information panel
Standard and Advanced
$200
Paved boarding area
Standard and Advanced
$7,000
Bench
Standard and Advanced
$3,000
Lighting
Standard and Advanced
$7,000
Trash and recycling bins
Standard and Advanced
$2,500
Shelter
Advanced
$4,000
Real-time sign
Advanced
$5,000
Interactive kiosk to request service and track vehicles
Advanced
$20,000
Bike rack
Advanced
$500
Wayfinding
Advanced
$500
Table 11 | Total Node Costs
Node
Unit Cost
Number of Units
Total Upfront Cost
Standard Node
$25,000
18
$450,000
Advanced Node
$45,000
2
$90,000
Total
20
$540,000
Technology Technology is a key component of the smart shuttle. The technology could provide several key features: Ability to accept pickup and drop off request via smartphone app, web platform, or telephone
Morrisville Public Transportation Study | 72