Part 4 Appendices 4.9 Review Schedules
B. Legislative Review Schedules
1. Comprehensive Plan Amendment and General Rezoning
Comprehensive Plan Amendment and General Rezoning Review Schedule
Town Council Decision Meeting [8][9]
Planning & Zoning Board Meeting [8]
Town Council Public Hearing [8]
Deadline to Enter Monthly Review Cycle
Staff Report Posted to the Web
Town Council Meeting [8]
Initial Staff Review
07/01/2016
08/01/2016
09/02/2016 09/08/2016 10/11/2016 10/25/2016 11/08/2016
10/03/2016
11/03/2016
12/02/2016 12/08/2016 01/10/2017 01/24/2017 02/14/2017
12/16/2016
02/02/2017
03/03/2017 03/09/2017 04/11/2017 04/25/2017 05/19/2017
04/03/2017
05/03/2017
06/02/2017 06/08/2017 07/11/2017 07/25/2017 08/08/2017
07/03/2017
08/02/2017
09/08/2017 09/14/2017 10/10/2017 10/24/2017 11/14/2017
10/02/2017
11/01/2017
12/08/2017 12/14/2017 01/09/2018 01/23/2018 02/13/2018
Pre-Application Conference [2] Submit Application [3][4] 12/15/2017 04/02/2018
02/01/2018
03/02/2018 03/08/2018 04/10/2018 04/24/2018 05/08/2018
Revisions to Application [7]
Completeness Review [5][6]
05/02/2018
06/08/2018 06/14/2018 07/10/2018 07/24/2018 08/14/2018
Pre-Application Materials Deadline [1] 07/02/2018
08/01/2018
09/07/2018 09/13/2018 10/09/2018 10/23/2018 11/13/2018
10/01/2018
10/31/2018
12/07/2018 12/13/2018 01/08/2019 01/22/2019 02/12/2019
Notes: [1] At least two business days before a scheduled pre-application conference, the applicant shall submit a conceptual plan or drawings showing the location, general layout, and main elements of the proposed development application. [2] A pre-application conference with staff is required or strongly encouraged for all applications (see UDO for specific application requirements). It is recommended to have a pre-application conference at least six weeks prior to application submittal. [3] Complete applications can only be dropped off at the Planning Department (260 Town Hall Drive, Suite B, Morrisville, NC 27560) on Wednesdays between 8 am and noon. See checklist and Section 2.4.3, Application Submittal, Acceptance, Revisions, and Withdrawal, of the UDO for specific requirements. [4] The Town recommends dropping off a complete application 2-3 weeks prior to date listed in the Deadline to Enter Monthly Review Cycle. Dropping off an application prior to the deadline date does not guarantee an application will enter that review cycle. [5] Staff provides the applicant written notice of submittal deficiencies or submittal acceptance by Friday (2 days). Review of an application does not start until staff determines it to be complete, accepts the application for review, and enters an application into the monthly review cycle. [6] Time needed to correct application submittal deficiencies and resubmit a complete application is the responsibility of the applicant. If the applicant fails to resubmit a complete application within 30 days, the application is considered abandoned. [7] This step typically occurs 1-2 times. Time needed to review revised applications varies with the extent of staff comments and responding revisions. If the applicant fails to submit a revised application within 15 days of receiving staff comments, the review time will most likely take longer than this published timeline. If the applicant fails to submit a revised application within 60 days (or staff-granted extension), the application is considered withdrawn. [8] Meetings are at 6:30 p.m. in the Town Hall Council Chambers (100 Town Hall Drive, Morrisville, NC 27560). [9] Staff provides applicant written notice of Town Council’s decision to approve the application, approve it with condition, or deny the application. The overall timeline is impacted by the complexity of the process and actions taken by the boards such as tabling an item or cancelling a meeting.
Morrisville, NC
July 1, 2016 Page 4-99